Skip to main content

Featured Post

Atlantic Yards/Pacific Park infographics: what's built/what's coming/what's missing, who's responsible, + project FAQ/timeline (pinned post)

From the latest Atlantic Yards Construction Alert: trucks coming for steel deliveries, concrete pour, but no dates specified

According to the latest two-week Atlantic Yards Construction Alert (bottom), dated 9/16/13 and distributed this morning by Empire State Development after preparation by Forest City Ratner, there will be 4 to 5 steel trucks per day when the steel is delivered to site of the B2 modular tower at Flatbush Avenue and Dean Street, and about 8 to 10 trucks per day will arrive during the two days that concrete cellar floor construction begins.

However, no dates for those events are specified.

An excerpt from the document:
B-2 Tower, Modular Residential
• Erection of Structural Steel within the B2 site and Dean Street transfer foundation area will continue during this reporting period. There will be approximately 4 to 5 steel trucks per day when the steel is delivered to the site. A separate logistics/site safety plan has been submitted for this work and approved by DOB. Conventional steel erection is scheduled for completion this month.
• Start installing formwork and rebar for the metal deck slabs, cellar and 1st floor
• Commence work related to the concrete cellar floors. Pour will take place over a two day period with approximately 8 to 10 trucks per day.
• Installing temporary power during this reporting period.
• Daily cleanup activities of sidewalks and streets are ongoing as required.
• Tentatively there are no construction activities scheduled for the upcoming Saturdays during this reporting period.

Atlantic Yards Construction Alert September 16 2013

Comments