Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
  • if market-rate construction is delayed, will the affordable housing also be delayed?
  • if so, what happens to the June 2014 agreement, reached by New York State and some community community negotiators, to guarantee--with penalties--the 2,250 units of affordable housing by May 2025, "subject to extensions set forth in the Development Agreement and the General Project Plan"? 
  • will affordable housing be built on sites previously planned for market-rate housing?
  • will covering the railyard for vertical construction be delayed? And doesn't that prolong blight?
  • how much tension is this causing between Forest City and its Shanghai-based partner?
  • beyond the three sites already up for sale/new investment, how much more might be sold?
  • will the developers seek more subsidies, or relaxed terms regarding the affordable housing?
Annotations as of October 2016
The announcement

According to the news release, Forest City, for the three months ended September 30, 2016, had a net loss of $430.9 million, or $1.67 per share, compared with a net loss of $302.2 million, or $1.18 per share, the previous year, mainly due to increased impairments:
The third-quarter net loss includes an impairment of non-depreciable real estate of $307.6 million, primarily related to Pacific Park Brooklyn. During the quarter, in light of changing market conditions directly impacting the Brooklyn residential market, the company, as part of a formal strategic plan update, made the decision to revise the overall project schedule to delay future vertical development. Given these market conditions and project timing, the company updated its estimated revenue, expense, cost and timing assumptions in its discounted cash flow model to estimate fair market value. The updated estimates no longer exceeded the carrying value of the asset, triggering the need for impairment. After the impairment, the company's remaining basis in its aggregate investment at Pacific Park Brooklyn is not material on a GAAP basis.-
(Emphasis added)

Note that Forest City, which is the minority partner in Pacific Park, had to jointly agree with joint venture partner/overseer Greenland USA, which owns 70% of the project/development rights going forward (excepting the arena and the 461 Dean tower). But no mention was made of a joint decision.

In a supplemental document filed with the Securities and Exchange Commission, the developer said that, regarding Pacific Park, it recorded "an impairment of $299.3 million ($266.0 million and $33.3 million allocated our projects under development and projects under construction, respectively."

CEO commentary

"We also recognized a significant impairment of Pacific Park Brooklyn as a result of our decision to revise the project schedule and related assumptions in light of evolving market conditions, including the impact of increased apartment supply, uncertainty surrounding 421A tax abatement and continued escalation in construction and trade costs," Forest City CEO David LaRue said in the statement.

In a separate 10-Q document filed with the SEC, the company added more explanation, acknowledging that the 550 Vanderbilt condo building is delayed:
During the three months ended September 30, 2016, it became evident the occupancy and rental rate declines in the Brooklyn market was determined not to be temporary as a result of an increased supply of new rental product amplified by the sun-setting and the uncertainty around the 421 A real estate tax abatement program. Over the last quarter, the condominium market in New York has also softened, causing the projected sale schedule for 550 Vanderbilt to be adjusted accordingly. Separately, the construction costs across the New York market continue to trend upward, resulting in increases in the estimated trade costs for certain infrastructure as well as vertical construction. In addition, the expiration of and the continued uncertainty related to the availability of the 421 A real estate tax abatement program puts further stress on anticipated returns.. the Company updated the discounted cash flow model to reflect the updated timing of the project schedule as well as the revenue, expense and cost assumptions. Based on the above, the estimated fair value of the investment no longer exceeded the carrying value. As a result, the Company recorded an other-than-temporary impairment of$299,300,000 during the three months ended September 30, 2016. The remaining basis in the investment (net of estimated future funding obligations) is not material.
No updated schedule was announced, but presumably there will be questions during today's conference call with investment analysts.

"While the Pacific Park Brooklyn impairment is a disappointment, revising the schedule to delay additional future vertical development reflects the tough decisions that are part of our disciplined approach to capital allocation," LaRue said. "As we have said before, we will activate new opportunities from our pipeline of entitlements only when and where we believe we can achieve an appropriate risk-adjusted return."

He made no mention of the affordable housing deadline.

Under construction

The press release cites three Pacific Park properties under construction:
  • 535 Carlton, a 298-unit, all-affordable apartment community, is expected to begin phased opening in the fourth quarter of 2016.
  • 550 Vanderbilt, a 278-unit condominium property, is expected to begin phased opening in the first quarter of 2017.
  • 38 Sixth Avenue, a 303-unit, all-affordable apartment community with 6,000 feet of street-level retail, is expected to begin phased opening in the second quarter of 2017.
There seem to be some delays, however. A separate 10-Q document filed with the SEC offers the following timetable. Note that "100% affordable" 535 Carlton could take a year to fill up, until the fourth quarter of 2017, as could the similar 38 Sixth Avenue, starting in the second quarter of 2017. Meanwhile 550 Vanderbilt is supposed to open in the first three quarters of 2017.


Is modular tower open?

The document, oddly enough, said that, in the third quarter of this year, Forest City opened two new properties, including "461 Dean Street, a 363-unit apartment community at Pacific Park Brooklyn."

Actually, it's by no means open. The Supplemental document says construction is complete and that, as of 9/30/16, 160 of the 363 units had received a certificate of occupancy.

According to p. 50 of the Investor Presentation below, as of 10/27/16, the developer has a 3% lease commitment at 461 Dean. Presumably that applies to the 50% market-rate units, and/or the retail, not the 50% below-market "affordable" units, for which there was a lottery.


Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.

Forest City's plans unc…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…